Traffic and
Transportation Sector - Investment Plan (2006-2012) - Rupees in Crores
Sl No |
Name of Project |
Length in KM/Nos |
Amount in Crores |
2005-06 |
2006-07 |
2007-08 |
2008-09 |
2009-10 |
2010-11 |
2011-12 |
1 |
RFB
Projects (16 Nos), Improvement to NH Standard |
98.30 |
163.00 |
0 |
43 |
30 |
30 |
30 |
30 |
0 |
2 |
Outer
Ring Roads |
35.00 |
140.00 |
2 |
27 |
30 |
45 |
20 |
18 |
0 |
3 |
Inner
Ring Roads |
42.00 |
85.00 |
0 |
15 |
20 |
20 |
20 |
10 |
0 |
4 |
Link
Roads |
17.20 |
93.00 |
0 |
13 |
30 |
20 |
20 |
10 |
0 |
5 |
Roads
Through CBD Area |
26.00 |
37.00 |
0 |
14 |
10 |
10 |
3 |
0 |
0 |
6 |
Radial
Roads |
110.50 |
233.00 |
0 |
40 |
47 |
50 |
55 |
40 |
1 |
7 |
Water |
40.00 |
132.00 |
0 |
22 |
30 |
40 |
20 |
20 |
0 |
8 |
Secondary
Roads |
1316.20 |
661.00 |
0 |
110 |
119 |
120 |
150 |
150 |
12 |
9 |
Rail
Over Bridges |
19 |
332.00 |
0 |
72 |
100 |
120 |
40 |
0 |
0 |
10 |
FLY OVERs/ |
9 |
415.00 |
0 |
46 |
110 |
110 |
120 |
29 |
0 |
11 |
Bridges |
73 |
900.00 |
0 |
110 |
180 |
180 |
180 |
205 |
45 |
12 |
Multi
Level Parking |
39 |
59.00 |
0 |
7 |
20 |
20 |
12 |
0 |
0 |
13 |
Public
Comfort Centres connected to bus station and
traffic centres |
7 |
2.00 |
0 |
1 |
1 |
0 |
0 |
0 |
0 |
14 |
Moffusil Bus Terminals |
16 |
133.00 |
0 |
25 |
50 |
50 |
8 |
0 |
0 |
15 |
Peripheral
Parkings |
5 |
15.00 |
0 |
5 |
5 |
5 |
0 |
0 |
0 |
16 |
Truck
Terminals |
4 |
70.00 |
0 |
17 |
25 |
28 |
0 |
0 |
0 |
17 |
Pedestrian
crossing/ escalator facilities |
8 |
16.00 |
0 |
3 |
6 |
5 |
2 |
0 |
0 |
18 |
Road
Markings and Sign Boards |
LS |
14.00 |
0 |
5 |
3 |
3 |
3 |
0 |
0 |
19 |
Signals |
LS |
25.00 |
0 |
5 |
5 |
5 |
5 |
5 |
0 |
20 |
Waiting
Sheds |
LS |
6.00 |
0 |
3 |
3 |
0 |
0 |
0 |
0 |
21 |
Bus
Bays |
250 |
12.00 |
0 |
2 |
2 |
2 |
2 |
2 |
2 |
22 |
Inland
Water transport Terminals, Navigational aids, Canal dredgingand
scientific disposal |
36 |
48.00 |
0 |
6 |
15 |
20 |
7 |
0 |
0 |
23 |
Metro
rail, Viability Gap |
|
635.00 |
0 |
100 |
200 |
200 |
135 |
0 |
0 |
GRANT TOTAL |
|
4226 |
2 |
691 |
1041 |
1083 |
832 |
519 |
60 |
Traffic and Transportation strategy
Traffic and Transportation Sector - Strategic Action Plan (2006-2012)
Component |
Insti tution |
Activity |
2005-06 |
2006-07 |
2007-08 |
2008-09 |
2009-10 |
2010-11 |
2011-12 |
|
Planning, Reforms and Institutional Strengthening |
CoC |
Upgradation of
Traffic & Transportation Study for entire for the Designated area |
|
x |
|
|
|
|
|
|
GoK |
Constitution and Operationalisation of Greater |
|
x |
|
|
|
|
|
||
CoC |
Transport Assets and
utilities mapping using G.I.S. Technology |
|
x |
x |
x |
x |
x |
|
||
CoC, Police dept. |
Traffic and
Transportation Management using G.I.S. and G.P.S. technology |
|
x |
x |
x |
|
|
|
||
CoC, Police dept. |
Design and
Implementation of IEC campaign for improved traffic awareness |
|
x |
x |
x |
x |
x |
|
||
CoC |
Capacity building initiatives
for better traffic management |
|
x |
x |
x |
x |
x |
|
||
CoC/ Municipality/ Panchayath |
Provision of bus bays,
including waiting Sheds in identified locations including signage |
|
x |
x |
|
|
|
|
||
Signage improvement at
bus bays to streamline bus and passenger mobility |
|
x |
x |
x |
x |
x |
x |
|||
Development of bus
terminals, 16 Nos |
|
x |
x |
x |
x |
|
|
|||
Development of required
infrastructure (signage, signal system, separators, etc.) |
|
x |
x |
x |
x |
x |
|
|||
|
Inland Water Transport
Terminals, Major jetties 2 Nos, Minor jetties 36 Nos, Navigational Aids and Dredging of Water ways of 60 KMs |
|
x |
x |
x |
x |
|
|
||
|
Provision of MRTS
(length in km) |
|
x |
x |
x |
x |
|
|
||
Improved Safety, Service delivery and Customer Satisfaction by
providing better infrastructure |
CoC/ Municipality |
Road Fund Board Projects
(16 Nos), Improvement of existing roads to NH
Standard |
|
x |
x |
x |
x |
x |
|
|
Forming a new Outer
Ring Road for stream lining Traffic |
|
x |
x |
x |
x |
x |
|
|||
Development of Inner
Ring Roads for stream lining Traffic |
|
x |
x |
x |
x |
x |
|
|||
Forming a new Link
Roads for stream lining Traffic |
|
x |
x |
x |
x |
x |
x |
|||
Development of existing
Roads of CBD area |
|
x |
x |
x |
x |
|
|
|||
Development of Radial
Roads |
|
x |
x |
x |
x |
x |
x |
|||
Development of Water
front Roads |
|
|
x |
x |
|
|
|
|||
Development of
secondary roads of the City |
|
x |
x |
x |
x |
x |
x |
|||
Railway Over bridges 18
Nos |
|
x |
x |
x |
x |
|
|
|||
Bridges 72 Nos |
|
x |
x |
x |
x |
x |
x |
|||
Multi Level Parking 39 Nos
of 50 Passenger car capacity |
|
x |
x |
x |
x |
|
|
|||
Public Comfort Centres, 7 Nos |
|
x |
x |
|
|
|
|
|||
Peripheral Parking at
5 Places |
|
x |
x |
x |
|
|
|
|||
Truck Terminals 4
Places |
|
x |
x |
x |
|
|
|
|||
Road Markings and Sign
Boards |
|
x |
x |
x |
x |
|
|
|||
Signals |
|
x |
x |
x |
x |
x |
|
|||
Fly Overs
and |
|
x |
x |
x |
x |
x |
|
|||
Pedestrian Crossing
with Escalator Facilities |
|
x |
x |
x |
|
|
|
|||
Environemntal upgradation |
CoC |
Development of Green
Belts along the Road Margins |
|
|
x |
x |
x |
x |
x |
|
PCB, RTA |
Effective monitoring
and pollution check |
|
x |
x |
x |
x |
|
|
||
RTA, Traffic Police |
Impose ban the use of
air horns causing noise pollution |
|
x |
x |
|
|
|
|
||
Finance |
CoC/ Mun/Panch, state govt |
Constitution of Urban
Transport Development Fund |
|
- |
- |
- |
- |
- |
- |
|